Code | Description | Predecessors | Relationships | Lead/Lag | Resources | Duration | Early Start Date |
---|---|---|---|---|---|---|---|
1a | Contact Dion and Carlita | None | 0 | J,D,C .25 hr each | 2 d | 11/29 | |
1b | Host planning lunch | 1a | FS (Finish/Start) | 0 | J,D,C 2 hr each | 1 d | 12/1 |
1c | Develop and distribute schedule | 1b | FS | 0 | J 2 hr | 1 d | 12/2 |
1d | Make hotel arrangement in Atlanta | 1a | FS | 0 | J .5 hr | 1 d | 11/30 |
2a | Gather packing material | None | 0 | D 2 hr | 1 d | 11/29 | |
2bi | Contact van companies and get 3 bids | 1c | FS | 2 d | 12/3 | ||
2bii | 2bi | FS | 0 | J .5 hr | 1 d | 12/7 | |
2biii | Sign moving contract | 2bii | FS | 1 d | 12/8 | ||
2c | Pack small and delicate items | 1c 2a | FS FS | -1 | C 6 hr | 1 d | 12/3 |